Good books on defence project management are relatively uncommon. Good books on defence project management that are engaging and funny are even rarer.
You can see a lot by observing**
In March this year, Defense News ran a story on an expected cost overrun in the USN’s Ford class aircraft carriers currently under construction. Projected to cost an already eye-watering US$11.76 billion dollars, the first of class vessel is facing an overrun of another billion dollars by the time it launches in 2015. Needless to say, the USN and the Congress are staring each other down about the expected blowout.
But neither side should be surprised. If they had read and digested Norman Augustine’s eponymous book of ‘laws’ of defence procurement, they would have seen it coming. The book has a chart of cost growth in American aircraft carrier projects which shows unit costs steadily increasing over time, as is the case for most military hardware. Running a ruler over the graph and plotting the expected costs and delivery date for the new class is straightforward. The result is a point that sits squarely on the long-term trend line. Seen in that light, the Ford class hasn’t had a cost overrun at all—rather, the planning figure was (yet another) triumph of optimism over experience (see graph below, click to enlarge).
Graph. Augustine’s Law IX—the ‘final law of economic disarmament’ in action.
Augustine is a poacher turned gamekeeper, at various times being high up in defence industry or in a senior acquisition position inside the Pentagon. He’s an engineer by training, and that shows in his willingness to quantify conclusions and in his implicit devotion to evidence-based policy. As such, the book is full of valuable data that is used to demonstrate principles and trends in an engaging way.
And defence planners might well benefit from the lessons that he distils from the numbers. Despite the abundant evidence that he presents, the mistakes of history continue to be made anew by new generations of planners. The US Congressional Budget Office has observed that, in many cases, historical data provides a better basis for planning than the estimates made in the early days of projects.
Unless the next White Paper contains some very big surprises, Australia won’t be buying aircraft carriers any time soon. But we signed up the Joint Strike Fighter before the R&D had begun in earnest, and are now looking at a substantially bigger price tag than expected (of which more next week.) Again, Augustine wouldn’t be surprised. His study of 81 major projects finds that final costs exceed pre-R&D estimates by an average of 52%.
It’s not just costs that routinely overrun—Stephen Gumley commented during his tenure as Chief Executive Officer of the Defence Materiel Organisation that schedule was consistently more troubling to him than budgets. Augustine has a law for that as well. The average schedule performance of a large number of American R&D projects reduces down to the ‘law of unmitigated optimism’:
Any task can be completed in only one-third more time than is currently estimated.
(Law XXIII)
These aren’t just cheap shots (although there are a few of those sprinkled throughout) but deep truths, and some of the book’s conclusions go well beyond the realm of defence projects. By bringing together diverse data sets from a wide variety of disciplines, Augustine arrives at ‘laws’ that are general in their applicability, while being specifically relevant to defence planning. One such is the ‘law of insatiable appetites’:
The last 10% of the performance sought generates one-third of the cost and two-thirds of the problems.
(Law VII)
Another example, and one that might apply to the management of many a government department, concerns the relationship between the number of participants in an activity and the outcomes achieved. The diverse data set includes the number of air to air victories by RAF pilots in WWII, American football rushed touchdowns, academic paper authorship and arrest data for the Washington DC police. The resulting law is all too convincing:
One tenth of the participants produce at least one third of the output, and increasing the number of participants merely reduces the average output.
(Law XX)